DATE : April 2011 - July 2012
CLIENT : Flottweg
END USER : Sydney Water
$115k project
Design, supply and installation of new and modified starter panels and cabling for the upgrade of two new centrifuges for Glenfield Sewage Treatment Plant.
<
DATE : Nov 2011 - June 2012
CLIENT : MidCoast Water
END USER : MidCoast Water
$450k project
Design, Supply and Installation of new motor control centre, instrumentation, and PLC and SCADA controls for centrifuge dewatering system at Forster Sewage Treatment Plant.
<
DATE : Dec 2008 - Oct 2010
CLIENT : Abergeldie Young
END USER : Sydney Water Corporation
$330k project
Design and Installation of Electrical, Instrumentation and SCADA for the upgrade of Inlet Works, SBR and Chlorination at Winmalee Sewage Treatment Plant.
<
DATE : Feb 2005 - Feb 2007
CLIENT : Kruger Engineering
ENS USER : Sydney Water Corporation
$207k project
Electrical design and installation works associated with the addition of High Voltage Aeration Blower and associated instrumentation and PLC Control system
<
DATE : February - October 2007
CLIENT : Ward Civil Engineers Pty Ltd
END USER : MidCoast Water
$845k project
Electrical, Instrumentation and Controls Design and Construction for process upgrade of Sewage Treatment Plant at Wingham.
<
DATE : March - Sept 2000
CLIENT : John Young (Kelvinhaugh)
END USER : Sydney Water Corporation
$290k project
Electrical, Instrumentation and Controls Design and Construction for upgrade of Digester 7201 sludge heating and gas recirculation systems at Warriewood STP.