DATE : Feb 2020 - July 2021
CLIENT : Abergeldie Contractors
END USER : Hunter Water Corporation
$600k project
Detailed Design, Installation and PLC/SCADA programming for the replacement of four Sedimentation Tank Sludge Scrapers and associated instrumentation.
DATE : July 2018 - March 2019
CLIENT : John Holland Pty Ltd and MPC Group Pty Ltd
END USER : Essential Water and Water NSW
$570k project
Commissioning and Installation Co-ordination of all Electrical, Instrumentation, Controls & Telemetry requirements for four new Water Pumping Stations, Bulk Water Storage System and Offtake Valve Sites along the 350km water pipeline from the Murray River to Broken Hill.
DATE : Nov 2017 - Dec 2018
CLIENT : Abergeldie Contractors
END USER : Sydney Water
$100k project
Electrical, Instrumentation, Controls and Telemetry Design and Installation for the reroofing of Cecil Park Reservoir.
DATE : Jan 2013 - Oct 2014
CLIENT : Haslin Constructions
END USER : Nambucca Shire Council
$540k project
Design, Manufacture and Construction of new HV Power Supply, Switchboards, Instrumentation, Telemetry and Controls for Bowraville Off-River Storage Dam Site
DATE : Sept 2012 - Oct 2013
CLIENT : Ledonne Constructions
END USER : Nambucca Shire Council
$1.2M project
Design, Manufacture and Construction of new HV Power Supply, Switchboards, Instrumentation, Telemetry and Controls for ten Borefields Pump Stations and Headworks Transfer Pump Station and Valve Cluster at Bowraville Water Treatment Plant
DATE : March 2012 - June 2013
CLIENT : HUNTER WATER CORPORATION
END USER : HUNTER WATER CORPORATION
$1.8M project
Construction of new Switchroom including computer flooring, air-conditioning and fire suppression systems
Co-ordinated Replacement of Main Swithcboards, Motor Control Centres, PLCs and all field cabling and cable ladder system whilst maintaining full operational capabilities of Hunter Water's largest water treatment plant
DATE : Feb 2008 - June 2010
CLIENT : ECO Civil
END USER : EuroWater (Eurobodalla Shire Council)
$850k project
Electrical, Instrumentation, Controls and Telemetry Design and Installation to provide a total upgrade Raw Water Low Lift & High Lift Pump Stations, Dam Intake Structure & Chlorination Plants
Power reticulation, LV Starter refurbishment, Motor Replacement, Actuated Control Valves, Solar Panels, instrumentation, RTU radio telemetry, RTU/SCADA programming
DATE : January - November 2007
CLIENT : ActewAGL
END USER : ACTEW
$2.2M project
Electrical, Instrumentation and Controls Design and Installation to provide a total upgrade of the Electrical, Instrumentation, Monitoring and Controls Systems at Googong Water Treatment Plant and Raw Water Pumping Station
DATE : Nov 2003 - July 2006
CLIENT : Water Treatment Australia
END USER : ACTEW
$1.6M project
Total electrical design and install services for 90Ml/day Dissolved Air Flotation Filtration (DAFF) plant
Power reticulation, MCCs, instrumentation, FDIOs, SCADA/PLC programming, integration of legacy systems, online implementation, testing and commissioning
DATE : March 2001 - March 2005
CLIENT : Sydney Water Corporation
END USER : Sydney Water Corporation
$595k project
Design, supply and installation of High Voltage and Low Voltage Electrical and Mechanical Services, Instrumentation and Telemetry for the refurbishment upgrade of Allawah Water Pumping Station
DATE : Feb 2002 - Aug 2003
CLIENT : Reed Constructions Australia
END USER : Sydney Water Corporation
$432k project
Electrical and Controls Design and Construction, Testing and Commissioning of HV and LV Switchgear, Instrumentation and Controls associated with the expansion of Prospect Water Pumping Station WPS300 and Construction of Elevated Reservoir WS096